Beiträge von kartabella

    Please help!
    1. In my Outlook 2003 I had programmed a repeating meeting - daily at 9.00 -
    1 hour long - no final date.
    2. 1 week later (7 meetings already took place) I had manually changed the
    starting time of the next 3 meetings to 10.00 (daily, 1 hour long as well)
    3. 3 weeks after the first programming step I decided to define the final
    date of the meetings' series (changing the "no final date defined" option to
    "after 30 occasions").
    4. After defining the date ALL the 30 meetings' starting times were changed
    to 9.00, INCLUDING THOSE 3 meetings in the past, which took place at 10.00.


    What can I do to prevent Outlook 2003 from changing the repetitive meetings'
    times, which were changed manually in the past?


    Danke.
    Ich verstehe auch Deutsch.